The SP certification exam also examines the skills required to form and manage agile teams. This includes understanding the roles and responsibilities of team members, developing cross-functional and self-managing teams, and establishing effective communication and collaboration practices. With these skills, SP practitioners are equipped to lead and manage agile teams in a way that enables them to deliver high-quality products and services quickly and efficiently.
NEW QUESTION # 24
For fast and continuous feedback, the traditional testing (V-Model) needs to shift testing
- A. left
- B. down
- C. right
- D. up
Answer: A
NEW QUESTION # 25
According to the Agile Manifesto, Responding to Change is more important than ________________
- A. Individuals and Interactions
- B. Contract Negotiation
- C. Customer Collaboration
- D. Following a Plan
Answer: D
NEW QUESTION # 26
Who is at the center of the Seven Core Competencies of Business Agility?
- A. The Developer
- B. The Business
- C. The Customer
- D. The Economic Benefit
Answer: C
NEW QUESTION # 27
SAFe advocates to develop on demand and release on cadence.
- A. FALSE
- B. TRUE
Answer: A
NEW QUESTION # 28
ART exists in the Essential SAFe configuration
- A. TRUE
- B. FALSE
Answer: A
NEW QUESTION # 29
Story points express which of the following:
- A. Uncertainty
- B. Time
- C. Complexity
- D. Volume
Answer: A,C,D
NEW QUESTION # 30
How many are the Agile Manifesto values?
- A. five
- B. twelve
- C. four
- D. seven
Answer: C
NEW QUESTION # 31
How long is the Iteration Retrospective?
- A. 1 day
- B. 4 hours
- C. 30 to 60 minutes
- D. 2 to 3 hours
Answer: C
NEW QUESTION # 32
Who attends the Scrum of Scrum meetings?
- A. Agile Team
- B. Scrum Master
- C. All of the above
- D. Product Owner
Answer: B
NEW QUESTION # 33
Velocity is
- A. measurement for economic benefit
- B. business value delivered (monetary)
- C. average hours of work done by the team
- D. the rate (in story points) at which the team delivers
Answer: D
NEW QUESTION # 34
The number of items that can be finished per unit of time is called
- A. lead time
- B. velocity
- C. cycle time
- D. throughput
Answer: D
NEW QUESTION # 35
The Agile Manifesto consists of 4 values and how many principles?
- A. five
- B. twelve
- C. ten
- D. seven
Answer: B
NEW QUESTION # 36
Which of the following are characteristics of an Agile team?
- A. Hierarchical
- B. Cross-functional
- C. Big
- D. Self-organizing
Answer: B,D
NEW QUESTION # 37
What is at the roof of the House of Lean?
- A. Value
- B. Leadership
- C. Relentless Improvement
- D. Innovation
Answer: A
NEW QUESTION # 38
PI objectives do not need to be written down and verbal expression is enough
- A. FALSE
- B. TRUE
Answer: A
NEW QUESTION # 39
Which of the following are Extreme Programming (XP) quality practices?
- A. Correct All
- B. Collective Ownership
- C. Automated Testing
- D. Pair Programming
- E. Refactoring
Answer: A
NEW QUESTION # 40
Which of the following areas is the main concern of Product Management?
- A. Technology
- B. Human Resource
- C. Program Execution
- D. Content Management
Answer: D
NEW QUESTION # 41
_____________ Value Streams contain the steps and the people who deliver end-user value using the business Solutions created by the ________________ Value Streams
- A. Development, Customer
- B. Operational, Economic
- C. Operational, Development
- D. Development, Operational
Answer: C
NEW QUESTION # 42
How many SAFe configuration are defined?
- A. three
- B. four
- C. Five
- D. seven
Answer: B
NEW QUESTION # 43
During Iteration Planning, the Scrum Master presents the stories in order of priority and answers clarifying questions
- A. FALSE
- B. TRUE
Answer: A
NEW QUESTION # 44
How many members does SAFe recommend to be in one Agile team?
- A. 12 to 15
- B. 15 to 20
- C. 3 to 7
- D. 5 to 11
Answer: D
NEW QUESTION # 45
Architectural Runway includes existing code, hardware components, business infrastructure, etc. that enable near-term business features.
- A. TRUE
- B. FALSE
Answer: A
NEW QUESTION # 46
Kanban is a pull system
- A. TRUE
- B. FALSE
Answer: A
NEW QUESTION # 47
......
SAFe-Practitioner Exam Dumps - Free Demo & 365 Day Updates: https://www.passtorrent.com/SAFe-Practitioner-latest-torrent.html
Pass SAFe-Practitioner Exam with Updated SAFe-Practitioner Exam Dumps PDF: https://drive.google.com/open?id=1dD3-BajOhfRXlmI-srKgVD_v8blo2i-P