SAP C-TS410-2020 exam consists of 80 multiple-choice questions that need to be answered in 180 minutes. C-TS410-2020 exam covers various topics such as SAP S/4HANA Overview, Organizational Units, Master Data, Procure to Pay, Order to Cash, Plan to Produce, and Data Migration. C-TS410-2020 exam is designed to test the candidate's understanding of the SAP S/4HANA system and its integration with other systems, processes, and data sources.
NEW QUESTION # 13
Within a MRP net requirements calculation, which of the following are demand elements? There are 3 correct answers to this question.
- A. Sales order
- B. On hand inventory
- C. Purchase order
- D. Planned independent requirements
- E. Safety stock
Answer: A,D,E
NEW QUESTION # 14
What must you do in a purchase order to purchase a material for a cost center?
- A. Enter an account assignment category
- B. Enter a purchase order item category
- C. Change the account to a cost element
- D. Change the material type appropriately
Answer: A
NEW QUESTION # 15
What can be assigned to a profit center?
There are THREE correct answers for this Question
- A. Material
- B. Asset
- C. Company code
- D. Organizational unit
- E. Operating concern
Answer: A,B,E
NEW QUESTION # 16
What fields are required when you create a cost center? There are TWO correct answers for this Question
- A. Person responsible
- B. Department
- C. Hierarchy area
- D. Address
Answer: A,C
NEW QUESTION # 17
How do you use the result of a released standard cost estimate? There are THREE correct answers for this Question
- A. To calculate the plan costs in a production order
- B. To determine the base costs used to calculate overhead
- C. To update the current standard price in the material master record
- D. To calculate the price of an activity type
- E. To determine a material sales price in Sales and Distribution
Answer: A,C,D
NEW QUESTION # 18
When would you use a statistical key figure?
- A. To collect actual expenses for an area of responsibility
- B. To distribute primary expenses in a standard cost element
- C. To identify internal cost flows
- D. To use as a tracing factor in an assessment
Answer: B
NEW QUESTION # 19
What data must be linked to a cost center to derive segment accounting? Please choose the correct answer.
- A. Work Center
- B. Cost Center Category
- C. Cost Center Group
- D. Profit Center
Answer: D
NEW QUESTION # 20
What needs to be entered to create a business partner? There are TWO correct answers for this Question.
- A. Business partner type
- B. Partner functions
- C. Account group
- D. Business partner role
Answer: C,D
NEW QUESTION # 21
What are the integration points between a fixed asset and a cost center? There are TWO correct answers for this Question
- A. Asset acquisition
- B. Asset book value
- C. Asset creation
- D. Depreciation run
Answer: A,D
NEW QUESTION # 22
What can a successful MRP run create?
- A. Purchase orders
- B. Reservations
- C. Dependent requirements
- D. Planned independent requirements
Answer: C
NEW QUESTION # 23
What master data defines the quantity structure to create a standard cost estimate? There are TWO correct answers for this Question
- A. Routing
- B. Bill of material
- C. Activity type
Answer: A,B
Explanation:
D .Cost center
NEW QUESTION # 24
What needs to be entered to create a business partner? There are TWO correct answers for this Question.
- A. Business partner type
- B. Partner functions
- C. Account group
- D. Business partnerrole
Answer: C,D
NEW QUESTION # 25
In what step of the purchase-to-pay process is a purchase requisition generated?
- A. Source of supply determination
- B. Invoice verification
- C. Vendor selection
- D. Determination of requirements
Answer: D
NEW QUESTION # 26
What activities can an employee complete usingemployee self-service? There are THREE correct answers for this Question.
- A. Perform compensation planning
- B. Update banking information
- C. Enroll in a training course
- D. Recruit employees
- E. Enter work times
Answer: B,C,E
NEW QUESTION # 27
How can you post internal labor costs to a network activity? There are TWO correct answers for this Question
- A. Distribution
- B. Service entry sheet
- C. Activity allocation
- D. Confirmation
Answer: C,D
NEW QUESTION # 28
Which of the following sequences of the source-to-pay process steps are correct? Please choose the correct answer.
- A. 1. Determination of requirements
2. Purchase order handling
3. Handling of payments
4. Goods receipt
5. Invoice verification - B. 1. Vendor selection
2. Source of supply determination
3. Purchase order monitoring
4. Goods receipt
5. Handling of payments - C. 1. Source of supply determination
2. Vendor selection
3. Determination of requirements
4. Purchase order handling
5. Goods receipt - D. 1. Determination of requirements
2. Vendor selection
3. Purchase order handling
4. Goods receipt
5. Invoice verification
Answer: D
NEW QUESTION # 29
......