NEW QUESTION # 50
You create a revision for a maintenance event builder (MEB) scenario. Which of the following statements are correct? Note: Thereare 2 correct answers to this question.

  • A. You can assign a network to a revision.
  • B. You must use hierarchical task lists for the MEB scenario.
  • C. You can assign a hierarchical task list to the revision.
  • D. You must assign maintenance notifications to the revision.

Answer: C,D


NEW QUESTION # 51
You want to assign components to an equipment task list. There isno BOM assigned to the equipment. What is the prerequisite for using the free assignment of material?

  • A. Free assignment of material is always possible without any prerequisites.
  • B. Assign the BOM usage for free assignment of material in Customizing.
  • C. Assign the header material of a material BOM as assembly to atask list operation.
  • D. Assign the header material of a material BOM to the equipmenttask list header.

Answer: B


NEW QUESTION # 52
You want to create a new functional location. Which configurationsteps are required? Note: There are 2 correct answers to this question.

  • A. Define the functional location category.
  • B. Define the reference functional location.
  • C. Define the structure indicator.
  • D. Define the number range for the functional location category.

Answer: A,C


NEW QUESTION # 53
Which functionalities belong to the current portfolio of SAP Business Objects Business Intelligence? Note: There are 2 correct answers to this question.

  • A. SAP Crystal Reports
  • B. SAP Lumira
  • C. Plant Maintenance Information Systems (PMIS)
  • D. SAP QuickViewer

Answer: A,B


NEW QUESTION # 54
Which statements regarding a maintenance order with status RELare correct? Note: There are 3 correct answers to this question.

  • A. The planner can change estimated costs only at header level.
  • B. Shop papers can only be printed after the order release.
  • C. Goods receipts for external services can be entered.
  • D. The planner can change planned costs at operation level.
  • E. The controller can determine actual cost surcharges.

Answer: B,C,D


NEW QUESTION # 55
The maintenance engineer creates a strategy plan with the call object maintenance order. Shift factors are set to 100%. Which date is relevant for the calculation of future planned dates if the maintenance work is delayed?

  • A. Planned end date of the maintenance order
  • B. Technical completion date of the maintenance order
  • C. Date of the final time confirmation
  • D. Planned date of the next call, independent of maintenance orderdates

Answer: B


NEW QUESTION # 56
Which of the following statements are correct for SAP S/4HANACIoud - Asset Management? Note: There are 2 correct answers to this question.

  • A. You can configure SAP S/4HANA Cloud via the self-service configuration UI.
  • B. You have access to the SAP S/4HANA back end system.
  • C. You can configure SAP S/4HANA Cloud via the SAP Asset Intelligence Network.
  • D. You do NOT have access to the SAP S/4HANA back end system.

Answer: A,D


NEW QUESTION # 57
Which activities can the technician perform with the Repair Malfunction SAPUI5 app? Note: There are 2 correct answers to thisquestion.

  • A. Put in Process.
    Schedule
  • B. Release. Print
  • C. Release. Start Work
  • D. Complete. Close Report

Answer: C,D


NEW QUESTION # 58
You require stock material to carry out maintenance tasks. Whichof the following statements regarding material planning in the maintenance order are correct? Note: There are 3 correct answers to this question.

  • A. The pick list for materials can be printed before order release.
  • B. A control key for internal workforce is required when assigning stock material to an order operation.
  • C. Material can be assigned at order header level.
  • D. Material can be assigned at order operation level.
  • E. A goods receipt can be entered for a technically completed maintenance order.

Answer: B,D,E


NEW QUESTION # 59
A piece of equipment cannot be linked to a material. Determine whether this statement is true or false.

  • A. False
  • B. True

Answer: A


NEW QUESTION # 60
Which of the following are components of cloud-based SAP Intelligent Asset Management? Note: There are 2 correct answers tothis question.

  • A. Worker safety applications
  • B. SAP Asset Manager
  • C. SAP Work Manager
  • D. SAP Predictive Maintenance and Service

Answer: B,D


NEW QUESTION # 61
The technical completion of the current maintenance order was posted with a delay of 5 days. What happens to the next planneddate if you set the shift factor for early completion to 100%?

  • A. It is postponed by a full cycle (100%).
  • B. It is postponed by 5 days.
  • C. It will be 5 days earlier.
  • D. It is not shifted.

Answer: B


NEW QUESTION # 62
You are analyzing the data transfer of the cost center of an equipment. What are the possible data origins? Note: There are 2correct answers to this question.

  • A. The cost center of the related maintenance work center
  • B. The cost center of the superior equipment
  • C. The reference functional location of the superior functional location
  • D. The individual maintenance of the cost center in the equipment master record

Answer: B,D


NEW QUESTION # 63
Which functionalities are available in the SAP Asset Manager fora maintenance worker? Note: There are 2 correct answers to this question.

  • A. Display maps. Display and maintain technical objects
  • B. Confirm time sheets. Attach documents
  • C. Schedule resources. Change task list
  • D. Change BOM. Create a work order on the ESRI map

Answer: A,B


NEW QUESTION # 64
You create two maintenance packages and only one package should be executed at a time. Which parameter determines this?

  • A. Hierarchy
  • B. Offset
  • C. Subsequent buffer
  • D. Package sequence

Answer: A


NEW QUESTION # 65
Which functions are available in the Resource Scheduling for Maintenance Planners app? Note: There are 2 correct answers to this question.

  • A. Monitor maintenance order operations due in the next 4 weeks.
  • B. Schedule and dispatch maintenance operations by shifts.
  • C. Cancel dispatched maintenance order operations.
  • D. Print job papers from a maintenance order.

Answer: A,C


NEW QUESTION # 66
You need to create a new functional location. Which actions can you perform with the SAP Fiori app Create Technical Object? Note:There are 3 correct answers to this question.

  • A. Assign a subordinate piece of equipment.
  • B. Edit classification data and characteristics.
  • C. Assign documents.
  • D. Create a measuring point.
  • E. Change a reference location.

Answer: B,C,D


NEW QUESTION # 67
You want to create a maintenance order with an external order operation with service items. Which of the following statements arecorrect? Note: There are 3 correct answers to this question.

  • A. The actual value entry can only be recorded via the service entrysheet.
  • B. The assignment of service master records to an order operation is optional.
  • C. The assignment of a control key with the service indicator set is mandatory.
  • D. The assignment of a control key with the service indicator set is mandatory.
  • E. The usage of a model service specification is mandatory.

Answer: A,C,D


NEW QUESTION # 68
Which of the following statements about orders with operation account assignment (OAA) are correct? Note: There are 3 correct answers to this question.

  • A. The settlement rule is maintained on header level.
  • B. Overall costs are dynamically summed up on header level.
  • C. A technical object must be assigned to an order operation.
  • D. Purchase requisitions have the operation as account assignment.
  • E. Costs are only stored for the operation object.

Answer: B,C,E


NEW QUESTION # 69
What is the correct receiver object type for the settlement of arefurbishment order?

  • A. The fixed asset
  • B. The WBS element
  • C. The cost center
  • D. The material

Answer: D


NEW QUESTION # 70
Which parameter in the material master is a prerequisite for refurbishment?

  • A. Valuation type H (origin)
  • B. Valuation category C (condition-based)
  • C. Valuation class 8000
  • D. Valuation category B (in-house/external procurement)

Answer: B