Download SAP C-TS412-1909 Exam Dumps to Pass Exam Easily in 2022
Get 100% Real Free SAP Certified Application Associate C-TS412-1909 Sample Questions
SAP S/4HANA Project Systems Certification Exam Details:
| Passing Score | C_TS412_1909 - 51% |
| Reference Books | S4120 (SAP S/4HANA 1909) S4121 (SAP S/4HANA 1909) S4122 (SAP S/4HANA 1909) S4123 (SAP S/4HANA 1909) |
| Exam Code | C_TS412_1909 |
| Exam Name | SAP Certified Application Associate - SAP S/4HANA Project Systems |
| Duration | 180 mins |
| Number of Questions | 80 |
| Level | Associate |
NEW QUESTION 12
Budgeting is implemented for projects. The budget has been adjusted several times. What standard report type provides an overview of adjustments on the budget?
- A. Line item report for budgets
- B. Hierarchical report on budget updates
- C. Structure overview for budgets
- D. Cost element report on budget updates
Answer: A
NEW QUESTION 13
Dates
You want to exchange data between SAP Project System and Microsoft What interface do you use?
- A. The catalog interface.
- B. No interface to Microsoft Project is available.
- C. you do not need and interface. You can exchange data using object link.
- D. The EPS interface (External Project Software).
Answer: D
NEW QUESTION 14
Which sales documents can update planned revenues on WBS elements? Note: There are 2 correct Answers to this question.
- A. Sales order
- B. Billing
- C. Inquiry
- D. Quotation
Answer: A,D
NEW QUESTION 15
In your logistics project, you want to carry out the internal project work as soon as possible. What do you have to maintain in capacity requirements planning?
- A. Control key of an activity
- B. Capacity planner group in the network header
- C. Scheduling and capacity category
- D. Scheduling and distribution key
Answer: A
NEW QUESTION 16
Where can you define a network as "header-account-assigned" or "activity-account-assigned"?
- A. Network profile
- B. Parameters for the network type
- C. Network type
- D. Project profile
Answer: B
NEW QUESTION 17
Which object is used to allocate the costs from a claim to the project structure?
- A. Internal order
- B. WBS element
- C. Network activity
- D. Claim
Answer: C
NEW QUESTION 18
Where do you maintain the length of the project ID?
- A. Project type
- B. Project coding mask
- C. Special characters
- D. Project profile
Answer: B
NEW QUESTION 19
A service company uses project management and they complain that the system does not prevent their project managers from exceeding their budgets. What actions do you have to take to solve the problem?
- A. Activate commitment management in the project definition. Enter the budget in the master data of the top WBS element.
- B. Activate availability control in the assigned budget profile. Define the tolerance limits in customizing.
- C. Activate availability control for projects in the controlling area. Enter the plan data for each WBS element.
- D. Activate availability control for the WBS elements. Define the tolerance limits on each WBS element.
Answer: B
NEW QUESTION 20
Float time is calculated during scheduling. Which of the following statements about float time are correct? Note: There are 3 correct Answers to this question.
- A. Activities with the time constraint "Must start on" always have a negative float time.
- B. By default, critical activities have a float time, which is less than or equal to zero.
- C. The maximum size of a free float is as large as the total float of an activity.
- D. The float time of WBS elements is calculated by extrapolation.
- E. Float time can be negative.
Answer: A,B,E
NEW QUESTION 21
Which objects do you have to maintain to enable automatic assignment of material components to the project? Note: There are 2 correct Answers to this question.
- A. Material master
- B. WBS element
- C. Network activity
- D. BOM item
Answer: C,D
NEW QUESTION 22
In your project, you work with a network and external activities. You have created a purchase requisition. The corresponding purchase order is created as well. Now, you increase the quantity of the external activity. How does the system support this scenario?
- A. The purchase order is updated automatically to match the new quantity while saving the project.
- B. The purchase order can be updated in Goods Receipt for Purchase Order (MIGO).
- C. A workflow can be triggered to inform the purchasing group.
- D. The system automatically creates a new purchase requisition with the difference to the original quantity.
Answer: C
NEW QUESTION 23
Your customer's projects are subject to recurring changes of date. The assembly activity has an earliest start date of February 10 and lasts until February 20. The customer wants to assign a material component so that this will be in stock 5 days in advance. Note: Every day is a working day. What do you recommend to set up the requirement date for the component?
- A. Set up the requirement date manually as February 5.
- B. Set up the requirement date aligned with the activity finish date and an offset of 15 days.
- C. Set up the requirement date aligned with the activity start date and a negative offset of 5 days.
- D. Set up the requirement date aligned with the activity start date and an offset of 5 days.
Answer: D
NEW QUESTION 24
Which of the following actions can transfer actual costs for external processing? Note: There are 2 correct answers to this question
- A. Saving a goods receipt
- B. Saving a service entry shee
- C. Saving a supplier invoice
- D. Saving a purchase order
Answer: A,B
NEW QUESTION 25
What functions are available for period end closing in SAP Project System? Note: There are 3 correct Answers to this question.
- A. Confirmations
- B. Settlement
- C. Progress analysis
- D. Results analysis
- E. Milestone trend analysis
Answer: B,C,D
NEW QUESTION 26
You are using WBS elements and activities are NOT assigned. Which statements apply to the maintenance of the actual start and finish? Note: There are 2 correct Answers to this question.
- A. You can always maintain the actual start and finish date of a WBS element.
- B. You can always maintain the actual start if the WBS element has the status "Released" or "Partially released".
- C. You can only maintain the actual finish if all lower-level WBS elements have an actual finish date and the status of the WBS element is "Released".
- D. You can only maintain the actual start of a WBS element if the finish date is not maintained.
Answer: B,C
NEW QUESTION 27
You used reductions to reduce the scheduled duration of all internally-processed activities in your project. However,
the duration did not changed after overall network scheduling. What do you check? Note: There are 2 correct answers to this question
- A. If the appropriate reduction type is set in the parameters for network scheduling
- B. If the maximum reduction level is less than 100
- C. If the reduction strategy is set in the network header
- D. If the reduction strategy is set in each activity
Answer: A,B