[Dec 12, 2021] Free The Open Group Certification OG0-093 Exam Question [Q103-Q125]

Share

[Dec 12, 2021] Free The Open Group Certification OG0-093 Exam Question

OG0-093 dumps & The Open Group Certification sure practice dumps


Potential Candidates

The OG0-093 exam captures the professionals’ needs requiring a deep comprehension of the TOGAF 9 framework. This includes those working in the positions associated with architectural projects and their responsibilities related to the processes, such as planning, executing, developing, delivering, and operating projects. Also, the architects who need to be introduced to the framework are included. Though not strictly required, having an initial knowledge of the Enterprise Architecture is game changing.


Exam Details

OG0-093 exam. Which is also called TOGAF 9 Combined Part 1 and Part 2 contains a total of 48 questions in the English language. 40 of them are dedicated to the Level 1 exam and thus are provided in the multiple-choice form. Then, and the second part of the test is made up of 8 scenario-oriented and very difficult MCQ items. The whole exam should be completed within 2.5 hours, and the registration fee one should pay to enroll is $550.

There are no strict prerequisites for a candidate to sit for this test apart from knowing all the required topics. To succeed, one has to gain a 55% score in the first part of the exam and 60% in Level 2. Note that although the test is supervised, Part 2 has an open-book format and allows candidates to use an in-built electronic copy of the specifications. However, the Part 1 exam is closed-book.

Failing any one of the sections means that the candidate has to retake and pass the failed part before getting the certificate. Out of the 150 minutes given to tackle the questions, it is recommended for one to use 1 hour on the first part before proceeding to section 2, which runs for 1.5 hours. Once the candidate crosses to section 2, he or she cannot go back to section 1. Also, candidates are not supposed to take any breaks in between the parts of OG0-093 exam.


Here is the cost of The Open Group OG0-093 Exam

The cost of The Open Group OG0-093 is $495.

 

NEW QUESTION 103
Which one of the following best describes the purpose of ADM Phase E?

  • A. To manage requirements throughout the ADM
  • B. To define the initial implementation plans
  • C. To define the scope, identifying stakeholders and obtaining approvals
  • D. To develop the Technology Architecture
  • E. To perform architectural oversight for the implementation

Answer: B

 

NEW QUESTION 104
Which of the following describes a key objective of the Technology Architecture Phase?

  • A. To define the Transition Architectures needed to achieve the Target Architecture
  • B. To define technology components into a set of technology platforms
  • C. To select a set of technology products that will form the basis of a solution architecture
  • D. To develop a migration plan to deliver incremental capabilities
  • E. To define the solution architecture needed to support the Application Architecture

Answer: B

Explanation:
Section: Part 1

 

NEW QUESTION 105
Which of the following describes the TOGAF Technical Reference Model?

  • A. A Common Systems Architecture
  • B. A Foundation Architecture
  • C. An Industry-Specific Architecture
  • D. An Organization-Specific Architecture
  • E. A Solution Architecture

Answer: B

 

NEW QUESTION 106
What part of the Architecture Repository holds specifications to which architectures must conform?

  • A. Architecture Landscape
  • B. Enterprise Continuum
  • C. Standards Information Base
  • D. Governance Log
  • E. Reference Library

Answer: C

Explanation:
Section: Part 2

 

NEW QUESTION 107
Which one of the following statements about viewpoints is correct?

  • A. A viewpoint is used to create views in Phases E and F
  • B. A viewpoint is what a stakeholder sees
  • C. A viewpoint is used as a template to create a view
  • D. A viewpoint is always specific to an architecture

Answer: C

 

NEW QUESTION 108
In Phase D of the ADM cycle, if you are following the order of the steps defined and the current step is to
perform gap analysis, what is the next step?

  • A. Define candidate roadmap components
  • B. Conduct formal Stakeholder review
  • C. Create Architecture Definition Document
  • D. Resolve impacts across the Architecture Landscape
  • E. Develop Baseline Architecture

Answer: A

Explanation:
Explanation/Reference:
Reference http://pubs.opengroup.org/architecture/togaf91-doc/arch/chap12.html

 

NEW QUESTION 109
According to TOGAF, which of the following best describes how the Enterprise Continuum is used in organizing and developing an architecture?

  • A. It is used to describe how an architecture addresses stakeholder concerns
  • B. It is used to coordinate with the other management frameworks in use
  • C. It is used to identify and understand business requirements
  • D. It is used to provide a system for continuous monitoring
  • E. It is used to structure re-usable architecture and solution assets

Answer: E

Explanation:
Section: Part 1

 

NEW QUESTION 110
Which ADM phase defines the scope for the architecture development initiative and obtains approval to
proceed with the architecture development?

  • A. Phase D: Technology Architecture
  • B. Phase B: Business Architecture
  • C. Phase A: Architecture Vision
  • D. Preliminary Phase
  • E. Requirements Management

Answer: C

Explanation:
Explanation/Reference:
Reference: https://pubs.opengroup.org/architecture/togaf9-doc/arch/chap06.html

 

NEW QUESTION 111
In which part of the ADM cycle are building blocks evolved using a common platform of steps?

  • A. Phases Grid H
  • B. Preliminary Phase rid Phase A
  • C. Phases B, C and D
  • D. Phases E and F

Answer: C

Explanation:
Section: Part 1

 

NEW QUESTION 112
When determining the requirements for enterprise architecture work in the Preliminary Phase, which of the following is not a business imperative that should be considered?

  • A. Strategic Intent
  • B. Technical elegance
  • C. Business requirements
  • D. Forecast financial requirements
  • E. Cultural aspirations

Answer: B

 

NEW QUESTION 113
According to TOGAF, which of the following best describes Architecture Governance?

  • A. The lifecycle management of information and related technology used by an organization
  • B. The practice by which enterprise architectures are controlled at an enterprise-wide level
  • C. A method for designing an information system in terms of a set of building blocks
  • D. A framework for operational and change activity
  • E. A categorization mechanism for architecture and solution artifacts

Answer: B

Explanation:
Section: Part 1

 

NEW QUESTION 114
According to TOGAF, which document should incorporate the actions arising from the Business Transformation Readiness Assessment technique?

  • A. Implementation and Migration Plan
  • B. Architecture Requirements Specification
  • C. Architecture Road map
  • D. Implementation Governance Model
  • E. Communications Plan

Answer: A

 

NEW QUESTION 115
In the Preliminary Phase, which of the following drives the requirements and performance metrics when scoping the enterprise architecture work?

  • A. Solution architecture
  • B. Time horizon
  • C. Service level agreements
  • D. Architecture governance
  • E. Business imperatives

Answer: E

Explanation:
Section: Part 2

 

NEW QUESTION 116
Which of the following is described by the TOGAF Architecture Content Framework as a type of artifact that shows lists of things?

  • A. Catalog
  • B. Diagram
  • C. Building Block
  • D. Deliverable
  • E. Matrix

Answer: A

 

NEW QUESTION 117
According to TOGAF, when creating views for a particular architecture, what is the recommended first
step?

  • A. Refer to existing libraries of viewpoints, to identify one for re-use
  • B. Ensure completeness of the architecture
  • C. Develop views for the target architecture first
  • D. Design a viewpoint to address all stakeholder concerns

Answer: A

 

NEW QUESTION 118
Which of the following best describes the purpose of the Gap Analysis technique?

  • A. To determine service levels for the architecture
  • B. To identify commercial building blocks to be purchased
  • C. To validate nonfunctional requirements
  • D. To identify missing functionality
  • E. To establish quality metrics for the architecture

Answer: D

 

NEW QUESTION 119
Which of the following TOGAF components was created to enable architects to design architectures addressing Boundaryless Information Flow?

  • A. The Architecture Repository
  • B. The Enterprise Continuum
  • C. The TOGAF Technical Reference Model
  • D. The Integrated Information Infrastructure Model

Answer: D

Explanation:
Section: Part 1

 

NEW QUESTION 120
Which of the following does TOGAF describe as "the structure of components, their interrelationships, and the principles guiding their design and evolution over time"?

  • A. Model
  • B. View
  • C. Architecture
  • D. Deliverable
  • E. Artifact

Answer: C

 

NEW QUESTION 121
Which of the following is described by the TOGAF Architecture Content Framework as a type of artifact that shows relationships between things?

  • A. Diagram
  • B. Building Block
  • C. Deliverable
  • D. Matrix
  • E. Catalog

Answer: D

Explanation:
Section: Part 1

 

NEW QUESTION 122
In Phase G, what document establishes the connection between the architecture organization and the implementation organization?

  • A. Architecture Roadmap
  • B. Transition Architecture
  • C. Architecture Landscape
  • D. Architecture Contract
  • E. Requirements Impact Statement

Answer: D

 

NEW QUESTION 123
Scenario:
Please read this scenario prior to answering the Question
You are the Lead Architect for a firm that manufactures ball bearings used in industrial equipment applications. They have manufacturing operations in several cities in the United States, Germany, and the United Kingdom.
The firm has traditionally allowed each manufacturing plant to drive its own production planning systems.
Each plant has its own custom Materials Requirements Planning, Master Production Scheduling, Bill of Materials, and Shop Floor Control systems.
"Just In Time" manufacturing techniques are used to minimize wastes caused by excessive inventory and work in process. The increasingly competitive business environment has compelled the firm to improve its business capability to be more responsive to the needs of industrial customers. To support this capability, the firm has decided to implement an Enterprise Resource Planning (ERP) solution that will enable it to better coordinate its manufacturing capacity to match the demands for its products across all plants. In addition, there are also new European regulations coming into force to which their manufacturing processes must conform in the next six months.
As part of the implementation process, the Enterprise Architecture (EA) department has begun to implement an architecture process based on TOGAF 9. The CIO is the sponsor of the activity. The Chief Architect has directed that the program should include formal modeling using the Architecture Content Framework and the TOGAF Content Metamodel. This will enable support for the architecture tooling that the firm uses for its EA program.
The Chief Architect has stated that in order to model the complex manufacturing process it will be necessary to model processes that are event-driven. Also, in order to consolidate applications across several data centers it will be necessary to model the location of IT assets. In particular, the end goal is to have the single ERP application running in a single data center.
Currently the project is in the Preliminary Phase, and the architects are tailoring the Architecture Development Method (ADM) and Architecture Content Framework to fit into the corporate environment.
Refer to the Scenario
You have been asked to recommend a response to the Chief Architect's request to tailor the TOGAF Content Metamodel.
Based on TOGAF 9, which of the following is the best answer?

  • A. You recommend that the architecture team incorporates the Data and Services Extensions into their tailored Content Metamodel. This would allow modeling of the location of IT assets and ensure regulatory compliance for the manufacturing process. It will also allow for identification of redundant duplication of capability which will be needed for a successful consolidation to a single data center.
  • B. You recommend that the architecture team incorporates the Governance and Motivation Extensions into their tailored Content Metamodel. This would allow modeling of the target milestones they want to achieve with this consolidation of application to a single data center. These extensions will also enable demonstration of regulatory compliance for the manufacturing process.
  • C. You recommend that the architecture team incorporate the Process Modeling and Infrastructure Consolidation extensions into their tailored Content Metamodel. As the environment is process-centric this will enable them to model the manufacturing processes and store information to support regulatory compliance. It also includes views useful for managing the consolidation of applications into a single data center.
  • D. You recommend that the architecture team incorporate the Process Modeling and Governance extensions into their tailored Content Metamodel. This is suitable as this is a significant IT change that will impact its operational models. This will ensure that they include specific entities and attributes that will allow them to model the event-driven nature of the manufacturing processes more precisely.

Answer: D

 

NEW QUESTION 124
Scenario:
Please read this scenario prior to answering the question
Your role is consultant to the Lead Architect within a company that manufactures a variety of small electromechanical devices. As part of a corporate-wide Lean Manufacturing initiative, the company has defined a strategic architecture to improve its ability to meet consumer demand and improve its ability to manage its supply chain. The strategic architecture called for the consolidation of multiple Enterprise Resource Planning (ERP) applications that have been operating independently in several of the divisions' production facilities. The goal is to replace the functionality of the existing applications with a new ERP product running as a single instance in the company's primary data center.
The company has a mature enterprise architecture practice and uses TOGAF 9 for the basis of its architecture framework. In addition to the EA program, the company has a number of management frameworks in use, including business planning, portfolio/project management, and operations management. The EA program is sponsored by the CIO.
Each division has completed the Architecture Definition documentation required to tailor and configure the environment to meet its own specific manufacturing requirements.
The enterprise architects have analyzed the key corporate change attributes and implementation constraints. A consolidated gap analysis has been completed which has identified the gaps across the Business, Data, Application, and Technology domains. Based on the results of the gap analysis, the architects have reviewed the requirements, dependencies and interoperability requirements needed to integrate the new ERP environment into the existing environment. The architects have completed the Business Transformation Readiness Assessment started in Phase A.
Based on all of these factors they have produced a risk assessment.
Because of the risks posed by the complexity of the current environment, it has been determined that a phased approach is needed to implement the target architectures. The overall implementation process is estimated to take several years.
Refer to the Scenario
The Implementation and Migration Plan v0.l, the draft Architecture Roadmap, and the Capability Assessment deliverables are now complete. You have been asked to recommend the next steps to prepare the final Implementation and Migration Plan.
Based on TOGAF 9, which of the following is the best answer?

  • A. You would conduct a series of Compliance Assessments to ensure that the implementation team is implementing the architecture according to the contract. The Compliance Assessment should verify that the implementation team is using the proper development methodology. It should include deployment of monitoring tools and ensure that performance targets are being met. If they are not met, then changes to performance requirements should be identified and updated in the Implementation and Migration Plan.
  • B. You would assess how the plan impacts the other frameworks in use in the organization. Minimally, the plan should be coordinated with the business planning, portfolio/project management and operations management frameworks. You would then assign a business value to each project, taking into account available resources and priorities for the projects. Finally, you would generate the Implementation and Migration Plan.
  • C. You would apply the Business Value Assessment Technique to prioritize the implementation projects and project increments. The assessment should focus on return on investment and performance evaluation criteria that can be used to monitor the progress of the architecture transformation. You would confirm the Transition Architecture phases using an Architecture Definition Increments Table to list the projects. You would then document the lessons learned and generate the final plan.
  • D. You would place the strategic Architecture Definition and Transition Architectures under configuration control as part of the ongoing architecture development cycle. This will ensure that the architecture remains relevant and responsive to the needs of the enterprise. You would then produce an Implementation Governance Model to manage the lessons learned prior to finalizing the plan. You recommend that lessons learned be accepted by the Architecture Board as changes to the architecture without review.

Answer: C

Explanation:
Business Value Technique usually follows BTRA, and will fufil the requirement to phase approach by prioritizing projects and listing their execution using ADI table.

 

NEW QUESTION 125
......