
[Apr 14, 2024] CDCP Free Exam Questions with Quality Guaranteed
CDCP Free Exam Files Downloaded Instantly
NEW QUESTION # 16
Sprinkler heads used in computer rooms activate at what temperature?
- A. 70 C (158 °F)
- B. 27 °C (81 °F)
- C. 57 °C (135 °F)
- D. Only on direct contact with a flame
Answer: C
Explanation:
Sprinkler heads used in computer rooms activate at 57 °C (135 °F), which is the standard temperature rating for ordinary sprinklers. This is the temperature at which the heat-sensitive element of the sprinkler head, such as a glass bulb or a fusible link, breaks or melts, allowing water to flow from the sprinkler. Sprinkler heads are designed to activate only when exposed to a fire, not to ambient temperature fluctuations. Therefore, sprinkler heads should be installed at a sufficient distance from the heat sources, such as servers, racks, or ducts, to avoid accidental activation. Sprinkler heads should also be selected and installed in accordance with the relevant standards and codes, such as NFPA 13 and NFPA 75.
References:
1: CDCP Preparation Guide, page 24, section 2.4.3 2: Sprinkler Systems in Data Centers3, page 1, section 1 4:
Data Center Fire Protection5, page 1, section 2 6: Data Center Sprinkler System Design7, page 1, section 1
NEW QUESTION # 17
What is the most preferred unit of measure for cooling capacity?
- A. Horsepower
- B. BTU
- C. Watt
- D. Ton
Answer: C
Explanation:
Cooling capacity is the measure of a cooling system's ability to remove heat from a space. The most preferred unit of measure for cooling capacity is watt (W), which is the SI unit for power. Watt is defined as the amount of energy transferred or converted per unit time. One watt is equal to one joule of energy per second. Using watt as the unit of measure for cooling capacity allows for easy comparison and calculation of the cooling performance and efficiency of different cooling systems.
Other units of measure for cooling capacity are ton, BTU, and horsepower, but they are less common and less convenient than watt. Ton is a unit of measure that describes how much water at freezing temperature can be frozen in 24 hours, equivalent to 3.5 kW or 12,000 BTU/h. BTU (British Thermal Unit) is a unit of measure that describes the amount of heat required to raise the temperature of one pound of water by one degree Fahrenheit, equivalent to 0.293 W. Horsepower is a unit of measure that describes the rate at which work is done, equivalent to 746 W.
References:
*Data Centre Professional (CDCP®) Reference Materials, page 8, section 2.1.1
*Data Centre Professional (CDCP®) Preparation Guide, page 11, section 2.1.1
*Cooling capacity - Wikipedia
*Air Conditioner BTU Calculator
*Air conditioning 101: Basics, working principle and sizing ... - GlobalSpec
*How is cooling capacity measured? - Sage-Advices
*Everything You Need to Know About Cooling Capacity
NEW QUESTION # 18
What should be considered when using a direct air handler for a data centre?
- A. Space available inside the computer rooms as the air handler space requirement for the inside the Computer room is quite large.
- B. Cost of operation as power consumption on these units tend to be higher compared to traditional air conditioning technology.
- C. The availability of three-phase power due to the high power requirements of these air handler units.
- D. Temperature, humidity and contamination of the outdoor environment.
Answer: D
Explanation:
Direct air handlers are a type of cooling system that use outdoor air to cool the data centre. They draw in fresh air from outside, filter it, and supply it to the data centre at the desired temperature and humidity level. Direct air handlers can reduce the energy consumption and operating costs of data centres by eliminating the need for mechanical cooling or refrigeration. However, they also have some challenges and limitations that need to be considered. One of the main factors to consider when using direct air handlers for data centres is the temperature, humidity and contamination of the outdoor environment. Depending on the location and climate of the data centre, the outdoor air may not always be suitable for cooling the data centre. For example, if the outdoor air is too hot, too humid, or too polluted, it may not provide enough cooling capacity, or it may damage the IT equipment or cause corrosion. Therefore, direct air handlers need to have sensors and controls to monitor the outdoor air quality and adjust the airflow accordingly. They may also need to have backup cooling systems or supplementary cooling devices, such as evaporative coolers or heat exchangers, to cope with extreme weather conditions or peak loads.
References: Data Center Cooling: A Comprehensive Guide - Dgtl Infra, Carrier Data Center Cooling System
39DC, Dublin Data Center: Rooftop Air Handlers.
NEW QUESTION # 19
What is the purpose of a service corridor?
- A. To create a secure and conditioned environment where media can be stored in a controlled manner.
- B. It provides a safe, vented and secure area where standby generators can operate safely.
- C. It provides a secure area where supporting facilities can be serviced and monitored on a 24x7 basis without disturbing the computer room.
- D. It is a generic name for pathways leading to other rooms that contains facility supporting equipment like the UPS room, battery room, generator room etc.
Answer: C
Explanation:
A service corridor is a dedicated space within or adjacent to a data centre that allows access to the supporting facilities, such as power, cooling, fire suppression, security, and cabling systems, without interfering with the computer room operations. A service corridor helps to isolate the noise, vibration, heat, and dust generated by the supporting facilities from the sensitive equipment in the computer room. A service corridor also enhances the safety and efficiency of the maintenance and monitoring activities, as well as the flexibility and scalability of the data centre design.
References: EPI Data Centre Training Framework, CDCP Preparation Guide, Service Corridors Definition | Law Insider
NEW QUESTION # 20
Which formula can be used to define risk?
- A. Risk = Impact * Probability
- B. Risk = Time * Quality
- C. Risk = Security * Criminality
- D. Risk = Probability * Cost
Answer: A
Explanation:
According to the CDCP Preparation Guide1, risk can be defined as the product of impact and probability.
Impact is the measure of the negative consequences or losses that may result from a risk event, such as downtime, data loss, or damage to the data centre. Probability is the measure of the likelihood or frequency of a risk event occurring, based on historical data, expert judgment, or statistical analysis. By multiplying impact and probability, risk can be quantified and compared, which helps in prioritizing and mitigating the risks. For example, a risk event that has a high impact but a low probability may have the same risk level as a risk event that has a low impact but a high probability.
References:
1: CDCP Preparation Guide, page 25, section 2.5.1 2: Data center risk assessment: A decision-making tool3, page 1, section 1 4: Accounting for Risk in Your Data Center Design/Build Strategy5, page 1, section 1 6: A Novel Framework for Data Center Risk Assessment7, page 1, section 1
NEW QUESTION # 21
What is the minimum clearance space required below water sprinkler heads and nozzles of gas-based fire suppression systems?
- A. 120 cm / 47 inches
- B. 46 cm / 18 inches
- C. 64 cm / 25 inches
- D. 60 cm / 24 inches
Answer: B
Explanation:
The minimum clearance space required below water sprinkler heads and nozzles of gas-based fire suppression systems is 46 cm / 18 inches, according to the CDCP Preparation Guide1 and OSHA regulation 29 CFR
1910.159 © (10)2. This clearance space is necessary to ensure that the sprinkler spray or gas discharge can reach the fire and cover the protected area effectively. Any material or obstruction below this clearance space can interfere with the sprinkler or gas distribution and reduce the fire suppression performance. Therefore, building owners and managers should ensure that all storage and objects in the data centre are kept below this clearance space, and that the clearance space is maintained at all times.
References:
1: CDCP Preparation Guide, page 24, section 2.4.3 2: Clarification of OSHA regulation 29 CFR
1910.159©(10), Sprinkler ...3, page 1, section 1
NEW QUESTION # 22
What needs to be installed in the battery room when using Lithium-ion batteries?
- A. A proper ventilation system since Lithium-ion batteries produce highly flammable Hydrogen gas during charging.
- B. A battery management system to monitor and prevent unsafe temperatures during charging/discharging.
- C. A proper supply of distilled water.
- D. High capacity air-conditioning equipment since Lithium-ion batteries are sensitive to high temperatures, which can reduce their lifetime.
Answer: B
Explanation:
According to the EPI Data Centre Training Framework, lithium-ion batteries are becoming more popular in data centres due to their higher energy density, longer lifespan, and lower maintenance costs compared to lead-acid batteries1. However, lithium-ion batteries also have some drawbacks, such as higher initial cost, stricter safety requirements, and potential thermal runaway risks1. Therefore, a battery management system (BMS) is essential to monitor and control the voltage, current, temperature, and state of charge of each battery cell or module, and to prevent overcharging, over-discharging, or overheating23. A BMS can also communicate with the UPS system and provide information on the battery status, performance, and health2.
References: 1: EPI Data Centre Training Framework, Module 5: Power, Section 5.3.2: Battery Technologies, Page 5-19 2: Benefits of Lithium-ion batteries for data centers at the edge,Data Center Knowledge, Page 1 3:
Lithium-Ion Batteries in Data Centers, Data Center Systems, Inc, Page 1
NEW QUESTION # 23
Cost of Downtime can be classified as.
- A. Direct and Indirect
- B. Classified and Declassified
- C. Mean and Median
- D. Up and Down
Answer: A
Explanation:
Cost of downtime is the total amount of money lost due to a data centre outage or disruption. It can be classified into two categories: direct and indirect. Direct costs are the immediate and measurable expenses incurred during or after an outage, such as lost revenue, lost productivity, recovery costs, compensation costs, penalties, etc. Indirect costs are the long-term and intangible impacts of an outage, such as reputation damage, customer dissatisfaction, loss of market share, legal liabilities, etc. Both direct and indirect costs can vary depending on the type, duration, and severity of the outage, as well as the industry, size, and location of the data centre.
References:
*EPI Data Centre Training Framework1
*EPI Data Centre Competence Framework2
*Understanding the Cost of Data Center Downtime3
*Uptime Institute's 2022 Outage Analysis Finds Downtime Costs and Consequences Worsening
*[INFOGRAPHIC] The Cost of Downtime: 21 Stats You Need to Know
NEW QUESTION # 24
Which one of the following is used in Measuring Business Value?
- A. Reliability
- B. Scalability
- C. Upfront Cost
- D. Regeneration Cost
Answer: B
Explanation:
Measuring business value is the process of assessing the benefits and costs of IT investments and initiatives in relation to the strategic objectives and priorities of the organization. One of the factors that can be used to measure business value is scalability, which is the ability of a system or component to handle increasing workloads or demands without compromising performance, quality, or functionality. Scalability is important for business value because it enables the organization to adapt to changing market conditions, customer expectations, and growth opportunities. Scalability can also reduce operational costs, increase efficiency, and improve customer satisfaction. Therefore, scalability is one of the factors that can be used in measuring business value.
References:
*EPI Data Centre Training Framework1
*EPI Data Centre Competence Framework2
*Measuring the Business Value of IT3
*How to Measure the Business Value with Effective Data Quality Governance
*7 Rules for Demonstrating the Business Value of IT
NEW QUESTION # 25
Which one of the following is an example of Indirect Cost?
- A. Cost revenues
- B. System recovery
- C. Damaged brand perception
- D. Legal fees
Answer: C
Explanation:
Damaged brand perception is an example of an indirect cost because it is not directly related to a specific product or service, but rather to the overall reputation and image of the company. Damaged brand perception can result from various factors, such as poor quality, customer dissatisfaction, security breaches, or negative publicity. Damaged brandperception can affect the company's ability to attract and retain customers, partners, and investors, and thus reduce its profitability and competitiveness.
References: EPI Data Centre Training Framework, Indirect Cost: Definition and Example, What Is Indirect Cost? Definition, Types and Examples.
Learn more
1 indeed.com2 o
NEW QUESTION # 26
Do I need to check the local standards if I already comply to international standards?
- A. You need to check the local standards to ensure compliance to these standards.
- B. Compliance to only international standards is good enough as most local standards are derived from international standards.
- C. Local standards do not to be checked as some countries have too many local standards, which will slow down the data centre construction.
- D. Data centres only need to comply to international standards since they are connected to a worldwide international network infrastructure.
Answer: A
Explanation:
Data centre design and infrastructure standards can vary from country to country, depending on the local regulations, codes, and practices. Therefore, it is important to check the local standards before designing, building, or operating a data centre in a specific location. Compliance to only international standards may not be sufficient or adequate to meet the local requirements, which could result in legal, financial, or operational risks. For example, some countries may have stricter fire safety, environmental, or energy efficiency standards than the international ones. Some countries may also have different electrical standards, such as voltage, frequency, or plug types. By checking the local standards, you can ensure that your data centre is compliant, safe, and efficient in the local context.
References:
1: Data Center Design: Which Standards to Follow?2, page 1, section 1 3: The Most Important Data Center Design and Infrastructure Codes and Standards4, page 1, section 1 5: Explaining the new family of ISO Data Centre Standards6, page 1, section 1 7: Standards for data centre certification. Is a changing coming?8, page 1, section 1
NEW QUESTION # 27
An optical fiber cable comes with the specifications 50/125 um.
What do the numbers represent?
- A. The first number represents the required distance to single-phase power cabling; the second number represents the required distance to three-phase cabling.
- B. The first number represents the distance for a 10 Gb/s connection; the second number represents the distance for a 1 Gb/s connection.
- C. The first number represents the diameter of the core; the second number represents the actual diameter cable including the buffer and jacket.
- D. The first number represents the diameter of the core; the second number represents the diameter of the cladding in microns.
Answer: D
Explanation:
Optical fiber cables are composed of a core, a cladding, and a coating. The core is the central part of the fiber that carries the light signal. The cladding is the layer surrounding the core that reflects the light back into the core and prevents signal loss. The coating is the protective layer that covers the cladding and provides mechanical strength and environmental protection. The specifications of an optical fiber cable indicate the dimensions of the core and the cladding in microns (m), which are one millionth of a meter. For example, a
50/125 m cable has a core diameter of 50 m and a cladding diameter of 125 m. The coating diameter is usually
250 m, but it is not part of the specifications.
References: Multimode Optical Fiber Selection & Specification - Corning, Optical Fiber OM3 (50/125µm Multimode Fiber), 50/125 Graded-Index OM2 Optical Fiber - OFS
NEW QUESTION # 28
systems are designed specifically to protect the structure of a building.
- A. Pro-inert
- B. Water sprinkler
- C. Inergen
- D. Total Flooding
Answer: B
Explanation:
Water sprinkler systems are designed to protect the structure of a building from fire by suppressing or extinguishing the flames with water. Water sprinkler systems are typically installed in the ceiling or walls of a building and are activated by heat or smoke detectors. Water sprinkler systems can reduce the risk of fire spreading and causing structural damage to the building.
References:
*EPI Data Centre Professional (CDCP®) Preparation Guide, page 28
*Fire Protection Systems for Data Centers | EPI
NEW QUESTION # 29
Escape route signage should be placed where?
- A. At every door providing a pathway
- B. Only at emergency escape doors
- C. At every door including riser doors, doors of storage closets etc.
- D. Only at the main entrance of the data centre building
Answer: A
Explanation:
Escape route signage should be placed at every door providing a pathway to the exit or the assembly area, according to the CDCP Preparation Guide1 and the EU Safety/Health Signs Directive2. Escape route signage is used to guide the occupants of the data centre fromwherever they are in the building, via a place of relative safety (the escape route), to the place of ultimate safety (the assembly area). Escape route signage should not be limited to only emergency escape doors or the main entrance of the data centre building, as these may not be accessible or visible from all locations. Escape route signage should also not include doors that do not lead to the exit or the assembly area, such as riser doors, doors of storage closets, or doors of other rooms, as these may confuse or mislead the occupants. Escape route signage should be placed at every door that provides a pathway to the exit or the assembly area, and should indicate the direction and distance of the escape route using pictograms, arrows, and words. Escape route signage should also be designed and installed in accordance with the relevant standards and codes, such as BS 5499 and ISO 7010.
References:
1: CDCP Preparation Guide, page 24, section 2.4.3 2: EU Safety/Health Signs Directive3, page 1, section 1
NEW QUESTION # 30
Which design consideration should be implemented with an Inergen-based fire suppression system?
- A. To use Inergen only for fires which are not related to electrical power.
- B. Install the gas containers (tanks) close to the data centre.
- C. Install protective covers around the nozzles to avoid accidental gas dumps.
- D. Pressure relief valves are required in the room that needs protection.
Answer: D
Explanation:
A design consideration that should be implemented with an Inergen-based fire suppression system is to install pressure relief valves in the room that needs protection. Inergen is a clean agent fire suppression system that uses a mixture of inert gases (nitrogen, argon, and carbon dioxide) to displace the oxygen in the room and extinguish the fire. However, when Inergen is released into the room, it creates a sudden increase in pressure, which can damage the walls, doors, windows, and ceilings of the room. To prevent this, pressure relief valves are required to vent the excess pressure to the outside and maintain a safe pressure level inside the room.
Pressure relief valves should be designed and installed in accordance with the relevant standards and codes, such as NFPA 2001 and ISO 14520.
References:
1: CDCP Preparation Guide, page 24, section 2.4.3 2: Data Center Fire Suppression Systems Bring Unexpected Risk3, page 1, section 1 4: Inergen from Fire Eater - CSC Datacenter5, page 1, section 1 6:
Inergen Fire Suppression System7, page 1, section 1
NEW QUESTION # 31
IP protection grades consist of two numbers.
Which levels of protection do they describe and what is the best protection?
- A. First digit; protections against the ingress of solid objects. Second digit; protection against ingress of water/fluids. The lower the number the better the level of protection.
- B. First digit; protections against the ingress of water/fluids. Second digit; protection against ingress of solid objects. The higher the number the better the level of protection.
- C. First digit; protections against the ingress of water/fluids. Second digit; protection against ingress of solid objects. The lower the number the better the level of protection.
- D. First digit; protections against the ingress of solid objects. Second digit; protection against ingress of water/fluids. The higher the number the better the level of protection.
Answer: D
Explanation:
IP protection grades are a way of showing the effectiveness of electrical enclosures in blocking foreign bodies such as dust, moisture, liquids, and accidental contact. IP stands for Ingress Protection or International Protection, and it is defined by the international standard IEC 60529. IP ratings consist of the letters IP followed by two digits and an optional letter. The first digit indicates the level of protection the enclosure provides against access to hazardous parts and the ingress of solid foreign objects. The second digit indicates the level of protection the enclosure provides against the ingress of water or fluids. The higher the number, the better the level of protection. For example, IP65 means the enclosure is dust-tight and can withstand water jets from any direction. IP68 means the enclosure is dust-tight and can be submerged in water under specified conditions.
References: EPI Data Centre Training Framework, CDCP Preparation Guide, IP code - Wikipedia, [IP Ratings Explained | Ingress Protection Rating | IP Codes | Updated 2022]
NEW QUESTION # 32
What should be a consideration when having casters (rollers/wheels) or feet under the rack?
- A. Casters and feet should be of a soft material, for example rubber, to avoid damage to the raised floor tile.
- B. Skirts at the bottom of the rack to avoid air flow between the hot and cold aisles.
- C. Casters and feet should not be locked to ensure the racks are still able to be moved to another position.
- D. The casters and feet should be larger to avoid a too heavy point load on the floor tile.
Answer: D
Explanation:
The casters and feet under the rack are used to support the weight of the rack and its equipment, and to allow the rack to be moved if needed. However, the casters and feet should also be designed to avoid putting too much pressure on the floor tile, especially if the data centre uses a raised floor system. A too heavy point load on the floor tile can cause the tile to crack, deform, or collapse, which can damage the rack, the equipment, and the underlying infrastructure. To prevent this, the casters and feet should be larger, so that they can distribute the weight over a larger area and reduce the point load. The casters and feet should also be compatible with the floor type and the load rating of the floor tile.
References:
1: CDCP Preparation Guide, page 22, section 2.4.1.1 2: Raised Floor Design Considerations for Data Center3, page 1, section 1 4: [SOLVED] server rack on casters or feet5, page 1, section 1
NEW QUESTION # 33
When having two non-synchronized power sources, the ATS / STS need to be of the type:
- A. Break before make.
- B. Both an ATS and STS can never handle two non-synchronized sources.
- C. Both make before break or break before make can be used.
- D. Make before break.
Answer: A
Explanation:
When having two non-synchronized power sources, the ATS / STS need to be of the type break before make, which means that the switch disconnects from one source before connecting to the other source. This prevents any short circuit, back feed, or phase mismatch that could occur if the two sources were connected simultaneously. Break before make switches are also known as open transition switches, because they create a brief interruption in the power supply during the switching process. This interruption is usually acceptable for most ICT equipment, as they have internal power supplies or batteries that can handle the transient. However, if the interruption is not acceptable, then the two power sources need to be synchronized before switching, which requires a make before break switch, also known as a closed transition switch. Make before break switches connect to the second source before disconnecting from the first source, which ensures a seamless transfer of power without any interruption. However, make before break switches require that the two sources have the same voltage, frequency, and phase, which can be achieved by using a synchronization module or a phase-locked loop.
References:
1: CDCP Preparation Guide, page 17, section 2.3.1 2: STS in data centres - Borri3, page 1, section 1 4: Using Static Transfer Switches to Enhance Data Center ... - Donwil5, page 1, section 1 6: What is an Automatic Transfer Switch (Power)? | Ethan Banks7, page 1, section 1
NEW QUESTION # 34
Which type of copper wire is used for grounding the racks to the SRG?
- A. Thin copper cable to keep the cost low for grounding.
- B. Braided copper wire or flat copper strip.
- C. Thick copper cable to create better grounding.
- D. Copper cable with plastic insulation (isolation).
Answer: B
Explanation:
The type of copper wire that is used for grounding the racks to the SRG (signal reference grid) in a data centre is braided copper wire or flat copper strip, according to the CDCP Preparation Guide1 and various web sources234. Braided copper wire or flat copper strip are preferred over thin or thick copper cable for grounding purposes, because they havelower impedance and higher surface area, which allow better dissipation of electrical noise and interference. Moreover, braided copper wire or flat copper strip are more flexible and durable than copper cable, which make them easier to install and maintain. Braided copper wire or flat copper strip should be connected to the SRG using exothermic welding or other code-compliant methods, and should follow the relevant standards and codes, such as ANSI/TIA/EIA-607 and NFPA 70.
References:
1: CDCP Preparation Guide, page 23, section 2.4.2 2: Signal Reference Grid | Enterprise Data Center Design and Methodology5, page 1, section 1 3: Grounding System Ground Rod Stacking Installation - Rain Bird6, page 1, section 1 4: SmartRack Copper Bus Grounding Bar - Eaton Website7, page 1, section 1
NEW QUESTION # 35
Which one of the following is an example of Direct Cost?
- A. Legal fees
- B. Negative public relations
- C. Reduced customer satisfaction
- D. Damaged brand perception
Answer: A
Explanation:
Legal fees are an example of direct cost because they can be directly attributed to a specific project, product, or service. Legal fees are incurred for the purpose of obtaining legal advice, drafting contracts, resolving disputes, or complying with regulations related to the core business activity. Legal fees are not general overhead expenses that are shared by multiple cost objects.
References: EPI Data Centre Training Framework, CDCP Preparation Guide, Direct Cost - Overview, Examples, Tax Implications
NEW QUESTION # 36
is the arithmetic mean of time between the failing and the subsequent running of the system in a particular time period.
- A. MTTR
- B. MLBF
- C. MCBF
- D. MTBF
Answer: D
Explanation:
MTBF stands for Mean Time Between Failures, and it is the arithmetic mean of time between the failing and the subsequent running of the system in a particular time period. MTBF is a measure of reliability that indicates how often a system or component fails during its operation. MTBF can be calculated by dividing the total operating time by the number of failures over a given period. For example, if a system operates for 1000 hours and experiences 5 failures, the MTBF is 1000/5 = 200 hours.
References: EPI Data Centre Training Framework, CDCP Preparation Guide, MTBF, MTTR, MTTF, MTTA:
Understanding incident metrics - Atlassian
NEW QUESTION # 37
Which one of the following is a Natural Disaster?
- A. Human Error
- B. Blackouts
- C. Grid Failure
- D. Hurricanes
Answer: D
Explanation:
According to the CDCP® Preparation Guide, a natural disaster is a catastrophic event that is caused by natural forces and has a significant impact on human lives, property, and environment. Hurricanes are examples of natural disasters, as they are powerful storms that form over warm ocean waters and produce strong winds, heavy rain, storm surges, and flooding. Grid failure, blackouts, and human error are not natural disasters, but rather man-made or technological disasters that result from failures or errors in human systems or activities.
References: CDCP® Preparation Guide, page 9. Natural Disaster Readiness for Data Centers. EM-DAT - The international disaster database. PDC Global - Pacific Disaster Center.
NEW QUESTION # 38
......
Q&As with Explanations Verified & Correct Answers: https://www.passtorrent.com/CDCP-latest-torrent.html
Practice Exams and Training Solutions for Certifications: https://drive.google.com/open?id=1_Oo7TqtqOgfiCfqriSH5UU--nQ-WXlf4